Tuesday, January 22, 2013

Story Points are only one third of the reason for estimating


“One’s destination is never a place, but rather a new way of looking at things.”
From: Miller, H. (1957). Big Sur and the Oranges of Hieronymus Bosch

Assigning some Story Points to a User Story may seem like the point of agile estimation; however in my eyes it just signifies the end of the process. 

For me the goals of agile estimation are to build a shared understanding in the team of what the story is and to build team consensus around what the rough estimate in Story Points should be.

The journey that the team goes through to come up with the estimate, is more important than the number that is assigned at the end of the process. Sure the assigned estimate assists with planning, however the knowledge that the team gains during discussion will help with their understanding of what they are delivering, why and how they will go about it. I often hear discussions on topics such as: user needs, business value, design, potential new User Stories, testing approach, development approach, how this User Story fits into the Epic, which are all valuable.

Here is a brief summary of the benefits that the team gain by going through an agile estimation process.


Assigning Story Points to each User Story supports



  • Grooming – identify stories that are large / candidates for splitting, identifying inefficiencies such as splitting an 8 pointer into two 5 pointers – should we do it as an 8 pointer to save overall time?
  • Sprint planning – roughly creating a sprint backlog based on average velocity.
  • Sprint planning – switching User Stories of equal Story Points in/out, up/down priority.
  • Release planning – using the combination of average velocity and story points of remaining stories to provide a rough view of our status.



Discussions build a Shared Understanding, which supports



  • Grooming – effective ways of splitting a User Story into multiple User Stories.
  • User Story Planning – splitting user Stories into a set of tasks that will work for the whole team.
  • Development – design ideas, implementation approach, testing approach, etc.
  • Identifying issues – such as impediments, dependencies, etc.



Using consensus to arrive at the Story Points supports



  • Sprint planning – with a stable average velocity and consensus on the Story Point of each User Story, there will be less second guessing of what to pull into the sprint.
  • Commitment to delivering the Sprint Backlog – consensus around the estimate, leads the team owning the sprint commitment. i.e. “it was my estimate, so I will push to finish the story within the sprint”.

Sunday, May 27, 2012

Fast Estimation


Imagine you have just completed some Product Discovery work and have a pile of User Stories that need to be estimated. You look at the pile and think, wow that will take hours to estimate using Planning Poker. I just want rough estimates so that we can put together a release plan. We know the plan will change in the future, but we need some starting point. What can I do? 

The answer is Fast Estimation. 

Fast Estimation is derived from Planning Poker. With some preparation and a 1 hour workshop it is common for a team to estimate about 30 User Stories. Teams I have worked with have successfully used it to estimate new functionality, automation of processes, improvements to internal practices and organisational change work.

While estimation is the main objective of the Fast Estimation process, another significant benefit you get for free is Shared Understanding. By this I mean the discussions that occur help to clarify in the minds of the team members what work is required, how it inter-relates and how big the entire backlog is. The knowledge that is gained about the backlog as a whole can often be more valuable then the estimates assigned to individual User Stories.

Fast Estimation Process

Preparation
Write out the User Stories to be estimated onto Index Cards of the same colour. A short cut that often works well is to just write the Title of the User Story on the index card and have the details of the User Story on hand during the session (i.e. in an electronic tool, or a printed spreadsheet, etc).

Find one to five Reference User Stories. These are User Stories that are well understood by the team and will act as a reference point for the upcoming comparative estimation. Ideally the team will have recently completed those User Stories or have at least estimated them in Story Points. The Reference User Stories should have differing Story Points, ideally being in the 2 to 20 range. I recommend at least three reference User Stories and usually aim for five, however you can get away with one. The case where your team is new and does not have any reference User Stories; sounds like a topic for another day. If you are really stuck just pick a User Story that you think is 3 Story Points, and use that for your Reference User Story.


Write out the Reference User Stories onto Index Cards of a different colour to the cards used for the User Stories to be estimated.


Schedule a 1 hour meeting in a room that has a long table, big enough for the team to gather around.


During the workshop
Set the scene for the workshop by explaining the following points

  • The objective of the workshop is to roughly estimate this stack of User Stories (show them the stack of Index Cards so that they can see how many there are), this will help to emphasise that time is of the essence. 
  • Fast Estimation will only rough estimates for these User Stories. 
  • There will be lots of assumptions and hence the estimates will not be very accurate.
  • The team will get another chance to re-estimate these User Stories in normal grooming session prior to starting work on the User Stories.

Layout one set up Planning Poker cards on a long conference table in ascending order i.e. 0, 0.5 .. 110, ∞.  It is a good idea to leave more space between the lower / middle numbers as hopefully more of the User Stories will end up there. If there are lots of User Stories at the large end of the scale that is a whole different problem, good luck with that ;).

Place the Reference User Stories below the Planning Poker card that corresponds to its Story Points. As per the picture below.


Fast Estimation reference user stories placed, ready to start



Picture 1: Planning Poker cards and Reference User Stories, with un-estimated User Stories at the bottom.

Confirm with the participants that they understand the Reference User Stories and agree with the Story Points for each. You may need to adjust one or more of these. Once you progress past this point, do not change the Reference User Story – Story Points any more these are now set in stone.

Divide up the User Stories roughly and hand them out to the participants.

Give the participants a couple of minutes to quickly read their set of User Stories to themselves.

Pick someone at random and ask them to read out their User Story and then place it underneath the Planning Poker card that corresponds to their estimate. Only allow a brief time for this. Ask the group if they are happy with that estimate and discuss/move it as necessary. Encourage participants to move the card if they disagree and to explain their justification at the same time.

Fast Estimation first user story placed


Picture 2: First User Story Estimated

Ask the group if there are any similar User Stories in peoples stacks. If so, repeat step 8 for those User Stories. Once there are no more similar User Stories pick another person at random and repeat step 8 for that User Story.

Work your wait through all of the User Stories, placing and discussing, finding similar User Stories, etc. etc.

Once all of the cards are all in position you can quickly write the Story Point estimate on each Index Card and gather them up.
Fast Estimation all stories estimated




Picture 3: All User Stories estimated 

As a final wrap up to the meeting it is again worth mentioning that the team may need to re-estimate these User Stories using Planning Poker before taking them into a sprint planning meeting.

A variation I have tried that did not work as well
After handing out the index cards, everyone places their cards at once in a big rush of activity. Then the team discusses them and re-estimates them as appropriate. This approach raises the energy in the room but it is a bit more confusing. Individuals will find it confusing to place their cards without the understanding of the backlog that they build up while discussing the User Stories one by one. The benefit to this approach is that very rough estimates are assigned to all of the User Stories up front, so if you run out of time at least you have everything estimated.

Teaching Fast Estimation
I have an example game to teach people Fast Estimation which extends on the fruit estimation of Planning Poker that I learnt in the Certified Scrum Master course taught by Rowan Bunning.

Write out the following Items To Cook on Index Cards, and place ‘B.L.T’ your three Story Point Reference User Story  (I have found that due to the simplicity of these User Stories 1 reference story is enough). 

Ask the participant to estimate cooking these items from scratch. I.e. for Eggs Benedict they are expected to make their own hollandaise sauce. Guide them through the Fast Estimation process,  this game usually takes less then 10 minutes (provided the participants are familiar with Planning Poker and Story Points).

Items to Cook


  • Eggs Benedict
  • Tin Baked Beans
  • Fruit Salad
  • B.L.T.
  • Crispy skinned Salmon
  • Poached Eggs SoufflĂ©
  • Cheese Burger
  • 64 Cup Cakes
  • Garden Salad
  • Alacarte, 3 courses for two
  • Cheese Cake
  • Duck Ala orange
  • Caesar Salad
  • Alacarte, 3 courses for ten
  • Lasagne
  • Pineapple upside down cake
  • Burrito’s
  • Mashed Potato
  • Beef Korma
  • Banoffee Pie
  • Fish & Chips
  • 12 Fancy cup cakes


Interested in estimation?





Related Reading
I can recommend these blogs for other great approaches to estimating stacks of User Stories:



Training available in South East QLD, Australia

If this article was interesting to you, then your team would likely benefit from face to face training on Agile Estimation. I run a one-hour Agile Estimation training session, that is highly interactive, immensely fun and teaches the foundation of agile estimation along with how to effectively run Planning Poker as well as Fast Estimation. Please contact me to set up a training session for your team: andrewrusling@hotmail.com

Saturday, March 17, 2012

User Story Centric Stand ups

As a Scrum team learns to work closely together and to focus their efforts they tend to only have a couple of User Stories in progress at any one time. Working collaboratively with limited work in progress brings several benefits, namely increased shared understanding and a reduced risk of partially completing a User Story.

Unfortunately when Scrum Teams work closely together on a couple of User Stories, their Stand Up Meetings become disjointed. By this I mean that as each person answers the three questions, several people will need to speak out of turn to present a full view of what is occurring and what needs to be done.

Day 229. Lesson Seven, Disco For Old People.

The standard format for Stand Ups where each team member answers the three questions in turn is a Person Centric approach. The standard format is a great way to teach those new to Scrum what information they are expected to provide, what information they should seek and what planning they should carry out.

However when the Scrum team works closely together on User Stories the Person Centric Stand Up no longer represents how the team is working.

Teams use their task board to visually represent the work they are doing and how they do it. I recommend that Stand Ups should also represent how the team is working. Hence when a team is collaborating closely on their User Stories I recommend the team switches to User Story Centric Stand Ups.

User Story Centric Stand Ups

1. In priority order discuss each User Story
        A. As a team update the work that was done since last stand up.
        B. As a team plan the work for today.
        C. As a team discuss any impediments relating to the User Story.
2. Ask the team if there are any other tasks that have popped up.
3. Ask the team if there are any other impediments. I.e. Impediments not directly relating to a User Story.
4. Ask the team if everyone has a clear plan for what to work on next.


This Stand Up format fits in easily with teams that are used to answering the three questions and have moved onto collaborating around User Stories.

User Story Centric Stand Ups are not recommended for new teams, only for teams that are comfortable with the Person Centric Stand Up and work collaboratively around a couple of User Stories.


Photo by: Kris Anderson