A.k.a. Story Points
allow us to separate Estimation from Commitment
Story Points vs. Ideal Days
Story Points are an estimate of the Size of the Story. Where
Size is the combination of Complexity, Effort & Doubt:
- Complexity – Difficulty, hard algorithms, complex logic extra, abstract concepts.
- Effort – Raw effort / grunt work. I.e. Making a simple parameter change to hundreds of similar method calls.
- Doubt – Uncertainty around how will we build it or what it is that we need to build.
Ideal Days or Ideal Hours is an estimate of how long it will
take to complete the Story.
So while Story Points are made up of a single element:
‘Size’, Ideal Days are made up of two elements: ‘Duration’ and ‘Size’.
Story Points cannot be equated to Ideal Days/Hours because
they are made of different elements. i.e. Size vs. Duration & Size.
Here is an example that illustrates my point
Story A is estimated by the team to be 1 Story Point. Story
B is estimated by the team to be 8 Story Points. Suppose that we get our two
brand new graduates to work on Story A, while our two experienced Senior
Developers work on Story B. Story A is completed in 5 working days, Story B is
also completed in 5 days. Now suppose that we had given Story B to our new
graduates, while our experienced Senior Developers worked on Story A. In this scenario Story A is completed in 1 day, while our graduates will struggle on eventually delivering Story B after 30 days! While the Size of the Story remained the same the Duration to complete them varied dramatically based on who worked on the Story.
graduates, while our experienced Senior Developers worked on Story A. In this scenario Story A is completed in 1 day, while our graduates will struggle on eventually delivering Story B after 30 days! While the Size of the Story remained the same the Duration to complete them varied dramatically based on who worked on the Story.
Estimation vs. Commitment
We use Story Points because it allows the team to focus on
estimating one element; the Size of the Story. When sizing the Story we do not
have to consider Who will work on it, or consider Committing to the Story.
During Sprint Planning we decide which Stories to Commit to
the Sprint Backlog. This is where the team considers who will work on which
story; hence combing the elements of Size, Who & Duration.
Estimating in Story Points allows for Estimation and
Commitment to be separated, giving better results for each.
Interested in estimation?
- Fast Estimation
- Story Points are only one third of the reason to estimate
- Top Tips for Planning Poker
Training available in South East QLD, Australia
If this article was interesting to you, then your team would
likely benefit from face to face training on Agile Estimation. I run a one-hour
Agile Estimation training session, that is highly interactive, immensely fun
and teaches the foundation of agile estimation along with how to effectively
run Planning Poker as well as Fast Estimation. Please contact me to set up a
training session for your team: andrewrusling@hotmail.com